The building is protected throughout with a combination of Roof (5900) and in-rack (9200) Sprinkler heads.
The system was installed in two main phases, infrastructure, and water supplies as part of the new build construction and the in the rack which was a post-completion fitout once the new facility was up and running
In-rack protection was designed in accordance with the Alternative In rack Sprinkler system design principles of the FM Rules.
The in-rack Sprinkler protection system was installed 20 weeks post-rack build after the facility was commissioned and operating, so careful planning, co ordination and integration were key to delivering this successful project.
Sector
Retail
Client: Wren Kitchens
Protecting Wren Kitchens 910,000sq.ft. manufacturing plant.
Main contractor:
Buckingham
Standards:
FM Global
Services:
- 18,500 sprinklers
- 3x diesel pumps
- 2x 500m2 tanks
- 14 valve sets
Programme:
52 weeks
Year of completion:
2023