Hall and Kay Fire Engineering
Home » Case Study » One Nine Elms

One Nine Elms, a prestigious mixed-use development in London with a height of up to 57 storeys, required a robust and compliant fire protection system to ensure the safety of residents, hotel guests, and staff. Hall & Kay were contracted to design, supply, and install a comprehensive automatic sprinkler system, wet riser system, and gas suppression system, ensuring full compliance with UK fire safety regulations. 

We installed a full coverage automatic sprinkler system to protect the full development, complying with BS EN 12845 and BS 9251 for residential use. The sprinkler system is served by concrete storage tanks and a pump system. The tanks provide a minimum run time of 60 mins, ensuring an uninterrupted water supply. The primary fire pump was installed as an electric motor-driven fire pump with a standby diesel motor-driven pump to ensure redundancy in case of failure and jockey pumps to maintain system pressure, preventing unnecessary fire pump activation. 

A Wet Riser system was implemented for this project to provide a reliable water supply for firefighting operations across multiple floors. This included two wet riser tanks supplying water to the system, two automatic 3 stage wet riser pumps, landing valves at every floor level, allowing firefighters to access water instantly, and a 100mm rising main, ensuring efficient water distribution. 

For high risk areas such as electric rooms and communications hubs, a Novec 1230 gas suppression system was installed to provide rapid fire extinguishing without damaging sensitive equipment. The control panel features a 24 hour battery backup for reliability during power loss.

Our expertise ensured that One Nine Elms is protected by a cutting edge fire safety system, meeting all compliance standards while providing maximum safety for occupants. The combined sprinkler systems, wet riser, and gas suppression provide a multi layered fire protection strategy tailored to the unique needs of this high-rise development. 

Our Project Director, Rob, said “One Nine Elms has been a challenging project not only due to the complex design of both commercial and residential sprinklers, wet riser and gas suppression systems across two towers but also covid and financial issues with the developer led to work stoppages impacting construction progress. Looking back now to see the finished article is very rewarding and shows the hard effort both Hall & Kay and the other contractors made to achieve PC on this prestigious build.”

Sector

Retail, Commercial, Hotels, and Residential

Client 

R&F Properties 

Project Name 

One Nine Elms 

Location

Vauxhall, London

Main Contractor 

Multiplex Construction 

Standards 

BS EN12845 – Commercial Sprinkler

BS 9251 – Residential Sprinkler System

BS 9990 – Wet and Dry Risers

System Equipment 

230 m3 Sprinkler Tank

2 x Five Stage Sprinkler Pumps 

10 x Duplicate Wet Valves 

2 x Duplicate Dry Valves

140 Sprinkler Zones

5500 x Residential Sprinkler Heads

7200 x Commercial Sprinkler Heads

90 m3 Wet Riser Tank 

2 x 3 Stage Wet Riser Pumps 

114 Wet Riser Outlets

6 x Gas Suppression Systems (Novec 1230)

Year of Completion

2024

Related commercial case studies…

One Broadgate

One Broadgate

Comprehensive design and installation of fire protection systems for a multi-level commercial office and retail development in central ... Read more

Kings Cross S3

Kings Cross S3

Hall & Kay are proud to provide fire protection systems for another high-quality building as part of the Kings Cross regeneration. Read more

Bloom Clerkenwell

Bloom Clerkenwell

Providing a fully integrated security system to protect 145,000 sq ft of work, retail and amentity space. Read more

London Borough of Redbridge

London Borough of Redbridge

Protecting one of London’s greenest boroughs. Read more

The O2 Arena

The O2 Arena

We currently provide maintenance on behalf of Ansco Arena, for all fire protection systems within the arena and a number of individual ... Read more

The Hackney Empire

The Hackney Empire

We were tasked with fully upgrading the site's Access Control System from the existing legacy Sateon system via Site Guard to the ... Read more

Need help?